Telangana: Kaleshwaram barrages rehab from mid-November after CWC Oversight vetting on Oct 5
▤Summary
- Kaleshwaram barrages (Medigadda, Annaram, Sundilla) will be repaired from mid-November after CWC vetting of the plan
- Irrigation Minister N. Uttam Kumar Reddy: rehabilitation/restoration of Medigadda, Annaram and Sundilla barrages of Kaleshwaram Project to start second week of November; CWC Technical Oversight Committee to vet designs Oct 5; aim
- Designer scheme: foundation grouting, extended stilling basins, fresh cut-off walls—to fix energy-dissipation, foundation stability and under-seepage issues flagged by National Dam Safety Authority (NDSA) and experts
🎯Exam Relevance
For UPSC · TGPSC · APPSC aspirants
TGPSC GS: Kaleshwaram project, Dam Safety Act 2021.
అKey Terms · English–Telugu
Barrage – బ్యారేజీ
Dam safety – ఆనకట్ట భద్రత
Rehabilitation – పునరుద్ధరణ