Cabinet clears Green Energy Corridor Phase-III (₹1.86 lakh crore; 135 GW RE, first-ever 50 GWh BESS) and Rabi MSP 2027-28
▤Summary
- The Green Energy Corridor (GEC) is a Union transmission programme that builds intra-State lines and substations so renewable power can be evacuated into the grid; MSP is the Minimum Support Price the Centre announces for crops on CACP advice
- Union Cabinet approved the third phase of the Green Energy Corridor (GEC) to integrate up to 135 GW of renewable energy into State/UT grids by FY 2032-33 and address curtailment (grid operators limiting RE output for stability).
- Total outlay >₹1.86 lakh crore — ₹1.36 lakh crore for intra-State transmission systems; as a first, a dedicated ₹50,000-crore component to deploy 50 GWh of battery energy storage systems (BESS).
- CCEA approved MSP hikes for all mandated Rabi crops for marketing season 2027-28 with margins of 50% to 106% over the all-India weighted average cost of production (Agriculture Minister Shivraj Singh Chouhan); Safflower got the biggest hike: +₹675/quintal to ₹7,215/quintal (+10.3%)
- Mains — Significance: transmission and storage are the bottleneck for the 500 GW non-fossil target; Challenges: curtailment, State discom finances, BESS cost and import dependence; Way forward: intra-State grid planning, storage mandates, and MSP reforms beyond cost-plus (crop diversification, PM-AASHA)
🎯Exam Relevance
For UPSC · TGPSC · APPSC aspirants
Prelims: GEC phases, BESS, Rabi MSP figures; Mains GS3: energy transition & agricultural pricing; TGPSC CA: Economy & Budget, National Affairs
అKey Terms · English–Telugu
Green Energy Corridor – హరిత ఇంధన కారిడార్
Battery energy storage system / BESS – బ్యాటరీ శక్తి నిల్వ వ్యవస్థ
Curtailment – విద్యుత్ ఉత్పత్తి కోత
Minimum Support Price / MSP – కనీస మద్దతు ధర